An award on Contracting Bridge means a contractor picked your bid, or you picked a sub. It isn't the contract. The two companies sign their own written agreement, and Contracting Bridge isn't a party to it. This checklist covers what that agreement usually spells out, so nothing important is left to a handshake.
General information, not legal advice. Contract, payment, lien and licensing rules differ by state. Have a construction attorney in your state review your subcontract form.
The parties and the job
- Who's who. Legal company names, addresses, license numbers where your state requires them, and who signs for each side.
- The job. Job site address, owner or client name if it's shared, and the project number from Contracting Bridge so both records match.
Scope
- What's included. Attach or restate the scope, the plans and any addenda by number and date. The bid's notes, inclusions and exclusions belong here too.
- What's excluded. Anything the sub isn't doing, and who is: permits, dumpsters, disposal, protection, cleanup, patching after other trades.
- Materials. Who supplies what, brands and products, and who takes delivery.
Price and payment
- The price. Lump sum, unit prices or time and materials, and what it includes.
- When payment comes. At completion, net 15 or 30 after an invoice, progress draws, or a deposit. Contracting Bridge shows the payment terms the contractor posted; the subcontract is where they become binding.
- Retainage. The percentage held back, if any, and when it's released.
- Invoices and paperwork. What has to come with an invoice: lien waivers, inspection sign-offs, photos.
- Pay-when-paid. Whether the sub gets paid only after the owner pays the contractor. Courts treat these clauses differently from state to state.
Schedule
- Start and finish. The start window, the expected duration and any milestones.
- Delays. What happens when weather, another trade, the owner or material shortages hold things up.
- Site rules. Working hours, access, parking, storage, safety requirements and who to call on site.
Changes
- Change orders in writing. No extra work without a signed change order that states the added price and time.
- Hidden conditions. How rot, bad decking, old wiring or other surprises are priced once they're found.
Insurance and safety
- Coverage and limits. General liability, workers' comp, auto and umbrella limits. See what insurance subcontractors need.
- Certificate and endorsements. A current certificate made out to the contractor, and any additional insured or waiver of subrogation endorsements. See how to check a certificate.
- Indemnity. Who's responsible for claims caused by each side's work. Many states limit how broad these clauses can be.
Quality, warranty and closeout
- Standards. Manufacturer instructions, code and inspections, and who schedules them.
- Warranty. How long the workmanship warranty runs and how callbacks are handled.
- Punch list and final payment. What "complete" means, and the paperwork for final payment: final lien waiver, warranty documents, cleanup.
Lien rights
Subcontractors and suppliers often have the right to file a lien if they aren't paid, and many states set deadlines and notice requirements to keep that right. Lien waivers trade those rights for payment. Agree on which waivers are exchanged at each payment, conditional or unconditional, and use your state's forms where it has them.
Ending the agreement
- Termination. How either side can end it, the notice required, and how completed work is paid.
- Disputes. Whether disagreements go to mediation, arbitration or court, and where.
On Contracting Bridge
Once a job is awarded, the job tracker keeps milestones, a shared job log and photos in one place, and the job record puts the project, the winning bid, addenda, answered questions and milestones on one printable page. Attach it to your subcontract so both sides are working from the same scope.
General information, not legal advice.